Highveld thunderstorms are great for the mielies—but lethal for an ageing warehouse roof that’s already peppered with rust pin-holes. One good cloudburst and you’re juggling dripping pallets, stock-write-offs, and a team that suddenly knows how to play “dodgems” with buckets.
If the thought of stripping 5 000 m² of sheet metal makes your ops manager hyperventilate, relax: modern warehouse roof replacement can happen while forklifts still zoom below. Here’s the playbook.
1 | Start With a Night-Time Moisture & Fastener Audit
Infra-red scans after sunset reveal wet insulation and hidden corrosion without disrupting shifts or racking layouts. Document every leak, pop-screw and sagging purlin; that map becomes your phasing plan.(Tip: do it during a summer storm—free stress-test!)
2 | Choose the Right System: Overlay Retrofit vs. Full Strip
Overlay (Retrofit): New steel sheets and spacer bars go over the old roof. No exposure, minimal debris, and operations keep humming. A retrofit often shaves 20–30 % off project cost and meets insurers’ “new roof” definition when engineered correctly.
Full Strip-and-Replace: Best when the old deck is structurally shot or asbestos. Work in 500 m² zones so only one section is open at a time; tarps + night crews = dry stock by sunrise. Industry manuals recommend “stage-by-stage stripping to minimise interior exposure.”
3 | Phasing & Shift-Friendly Scheduling
| Phase | Crew Hours | Roof Area | Key Ops Benefit |
|---|---|---|---|
| Pre-lunch (07:00–12:00) | Safety lines, material hoist | 300 m² | Forklift lanes still open |
| Lunch lull (12:00–14:00) | Sheet removal / overlay | 200 m² | Staff canteen time = quiet roof below |
| Afternoon (14:00–17:00) | New sheets, flashings | 300 m² | Minimal noise; conveyors already loud |
| Night (18:00–01:00) | Seam sealing, thermal blanket | 200 m² | Zero human traffic under roof |
Repeat for ± 12 days and the whole 5 000 m² skin is swapped with no daytime shutdowns.
4 | Spec Industrial-Grade Materials Once—Cry Never
| Item | Recommended Spec | Why It Matters |
|---|---|---|
| Profile | Klip-Lok / Klip-Tite concealed-fix | No exposed screws = fewer future leaks (saisc.co.za) |
| Coating | 0.58 mm Chromadek® or ZincAL® | Class 4 hail rating, 20-year corrosion warranty (saisc.co.za) |
| Insulation | 40 mm PIR board + 135 mm glass-wool | Cuts summer heat by up to 12 °C (roofing-guarantee.co.za) |
| Walk-way mats | Non-slip aluminium | Keeps maintenance crews safe after hand-over |
5 | Budget Reality Check (2025 Gauteng Rates)
| Cost Block | R / m² | Est. Total (5 000 m²) |
|---|---|---|
| Supply-only 0.58 mm concealed-fix sheets | R260–R340 | R1.3 m – R1.7 m |
| Turn-key install incl. insulation & safety | R550–R900 | R2.75 m – R4.5 m |
Metal roofs for industrial sites typically run R350–R700 / m² installed, depending on profile complexity and downtime penalties.
6 | ROI Fast-Track: Why Management Signs the PO
1. Zero stock losses during project → immediate payback.
2. Energy savings: reflective coatings + insulation cut HVAC bills ± 15 % in Gauteng summers.
3. Solar-ready: concealed-fix ribs accept PV clamps—future-proofing for load-shedding mitigation.
4. Insurance brownie points: new Class-4 roof lowers premiums and excess.
7 | Case Snapshot: East-Rand Logistics Hub
- Scope: 4 800 m² Klip-Tite retrofit over rusted corrugated roof.
- Downtime: 0 h (night shifts & phased zones).
- Rain delays: 1 minor storm, contained with under-sheet tarps.
- Final result: 15-year watertight warranty; warehouse back to 100 % ops by week three.